S. No. Name of Project Installed Capacity Agency Year of completion Status
279. Revised Holi – II SHP- HP (Updated)   M/s Om Energy Generation Pvt. Ltd., Dehradun 2019 Completed
278. Sarda Sagar, Pilibhit, UP 1500 kW Uttar Pradesh Jal Vidyut Nigam Ltd., Lucknow 2017-18 Completed
277. Jani Escape SHP 2 X 1000 kW IWRD,UP Dec 2017 Completed
276. Haidarpur
Kesho Pur
Rithala-1
Rithala-2
Chandrawal-1 &
Chandrawal-2
Wajirabad
100 kW
…..kW
50 kW
60 kW
52 kW &
28 kW
130 kW
Delhi Jal Board, Govt. of NCT of Delhi, Delhi 2016-17 Completed
275. Vasna, Ahmedabad Sewage fall SHP 80 kW Taparia Aqua Industries Pvt. Ltd., Ahmedabad 2016 Completed
274. Dada MHP in Dehrdun 1 X 50 kW UREDA, Uttarakhand June, 2015 Completed
273. Baram MHP in Pithoragarh 2 X 500 kW UREDA, Uttarakhand April, 2015 Completed
272. Hemkund in Chamoli 2 X 250 kW Uttarakhand Aug. 2012 Completed
271. DPR , Stable Power Evacuation System Agnoor, Belsar, Walidad & Arwal SHP's   Bihar Aug. 2011 Completed
270. DPR, Stable Power Evacuation System Jainagra, Shrikhinda, Amethi, Natwar & Rampur SHP's   Bihar Apr. 2011 Completed
269. DPR, Stable Power Evacuation System for Dehra, Tejpura, Sipaha   Bihar Apr. 2011 Completed
268. DPR, Stable Power Evacuation System for helabag, Nasariganj, Paharma, Sabari   Bihar Apr. 2011 Completed
267. Mathauli SHP     Mar. 2011 Completed
266. Gaundar MHP   Uttarakhand Feb. 2011 Completed
265. Khajoori, Haryana 2700 kW M/s Puri Oil Mills Ltd., New Delhi 2011 Completed
264. Mainmatti, Haryana 2250 kW M/s Puri Oil Mills Ltd., New Delhi 2010-11 Completed
263. Khara Small Hydro Electric Scheme 1500 kW Uttar Pradesh Jal Vidyut Nigam Ltd., Lucknow 2010-11 Completed
262. Chakshi   Himachal Pradesh Oct. 2010 Completed
261. Kanhar HEP, Chhattisgarh 50 MW Chhattisgarh State Electricity Board, Raipur, Chhattisgarh 2009-11 Completed
260. Rangat, A&N Island 150 kW A&N Administration, Electricity Department, NRSE Division, Port Blair 2009-2011 Completed
259. Panchvati, A&N Island 100 kW A&N Administration, Electricity Department, NRSE Division, Port Blair 2009-2011 Completed
258. Vasundhra, A&N Island 10 kW A&N Administration, Electricity Department, NRSE Division, Port Blair 2009-2011 Completed
257. Kamsarath, A&N Island 10 kW A&N Administration, Electricity Department, NRSE Division, Port Blair 2009-2011 Completed
256. Krishna Nallah, A&N Island 40 kW A&N Administration, Electricity Department, NRSE Division, Port Blair 2009-2011 Completed
255. Holi-II SHP in Himachal Pradesh   Krishna Hydro Power Projects Pvt. Ltd., Dehradun Mar. 2010 Completed
254. Study Regarding Restoration of MDDL of Rihand Reservoir   Central Electricity Authority, Ministry of Power, New Delhi Mar. 2010 Completed
253. Revised DPR of Chakshi SHP 1 X 2000 kW Puri Oil Mills Ltd., New Delhi Mar. 2010 Completed
252. Kalpong, A&N Island 500 kW A&N Administration, Electricity Department, NRSE Division, Port Blair 2009-2010 Completed
251. Korang, A&N Island 200 kW A&N Administration, Electricity Department, NRSE Division, Port Blair 2009-2010 Completed
250. Athunli MHP 1 X 10 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
249. Aya MHP 1 X 25 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
248. Ayu MHP 1 X 10 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
247. Eyi MHP 1 X 10 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
246. Jheblum MHP 1 X 10 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
245. Jonkey MHP 1 X 25 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
244. Kathang MHP 1 X 25 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
243. Lama MHP 1 X 10 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
242. Lama MHP 2 X 10 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
241. Langa MHP 2 X 50 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
240. Ledi Ishi MHP 1 X 15 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
239. Melong MHP 2 X 25 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
238. Melong Kang MHP 1 X 25 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
237. Muju MHP 1 X 50 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
236. Pacho MHP 2 X 25 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
235. Pallu MHP 2 X 50 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
234. Pame Sire MHP 2 X 50 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
233. Para-II MHP 1 X 25 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
232. Parchang MHP 1 X 15 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
231. Patta Nallah 2 X 50 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
230. Purchi MHP 2 X 50 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
229. Sup MHP 1 X 25 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
228. Tahin MHP 2 X 50 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
227. Tape MHP 1 X 10 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
226. Yorko MHP 2 X 5 kW MNRE, New Delhi and DHPD, Arunachal Pradesh Apr 2009 - Mar 2010 Completed
225. Nigolgad MHP 1 X 100 kW UREDA, Uttarakhand Oct 2009 Completed
224. Haflagad MHP 1 X 200 kW UREDA, Uttarakhand Aug 2009 Completed
223. Para-II MHP in East Kameng District 1 X 25 kW Arunachal Pradesh Aug 2009 Completed
222. Lama MHP in East Kameng 1 X 10 kW Arunachal Pradesh Aug 2009 Completed
221. Purchi MHP in Kurung Kumey 2 X 50 kW Arunachal Pradesh Aug 2009 Completed
220. Langa MHP in Kurung Kumey 2 X 50 kW Arunachal Pradesh Aug 2009 Completed
219. Pame Seri MHP in West Siang 1 X 25 kW Arunachal Pradesh Aug 2009 Completed
218. Eyi MHP in Dibang Valley 1 X 10 kW Arunachal Pradesh Jul 2009 Completed
217. Athunli MHP in Dibang Valley 1 X 10 kW Arunachal Pradesh Jul 2009 Completed
216. Tape MHP in Dibang Valley 1 X 10 kW Arunachal Pradesh Jul 2009 Completed
215. Aya MHP in Lower Dibang Valley 1 X 25 kW Arunachal Pradesh Jul 2009 Completed
214. Ayu MHP in Lower Dibang Valley 1 X 10 kW Arunachal Pradesh Jul 2009 Completed
213. Sile Sokong MHP in West Siang District 1 X 15 kW Arunachal Pradesh Jul 2009 Completed
212. Genung MHP in Upper Subansiri 1 X 25 kW Arunachal Pradesh Jul 2009 Completed
211. Sup in Anjaw 1 X 25 kW Arunachal Pradesh Jul 2009 Completed
210. Khathang in Anjaw 1 X 25 kW Arunachal Pradesh Jul 2009 Completed
209. Jheblum in Anjaw 1 X 10 kW Arunachal Pradesh Jul 2009 Completed
208. Myntriang SHP Stage –I in Karbi Anglong District 2 X 3 MW Assam Jun 2009 Completed
207. Patta Nallah MHP in East Kameng District 2 X 50 kW Arunachal Pradesh Jun 2009 Completed
206. Tahin MHP in Tirap District 2 X 50 kW Arunachal Pradesh Jun 2009 Completed
205. Paya MHP in East Kameng District 2 X 50 kW Arunachal Pradesh Jun 2009 Completed
204. Jonkey MHP in Changlang District 1 X 25 kW Arunachal Pradesh Jun 2009 Completed
203. Ledi-Ishi Nacho MHP in Upper Subansiri District 1 X 25 kW Arunachal Pradesh May 2009 Completed
202. Wada MHP in East Kameng District 1 X 25 kW Arunachal Pradesh May 2009 Completed
201. Muju MHP in Kurung Kumey District 1 X 50 kW Arunachal Pradesh May 2009 Completed
200. Para-I MHP in East Kameng District 1 X 25 kW Arunachal Pradesh May 2009 Completed
199. Paidhar Rong MHP in Tawang Disctrict 1 X 25 kW Arunachal Pradesh May 2009 Completed
198. Yorko Rong MHP in Tawang Disctrict 1 X 25 kW Arunachal Pradesh May 2009 Completed
197. Gangi Reachak in Tehri Garhwal 2 X 100 kW Uttarakhand Feb 2009 Completed
196. Sumbachu DPR in Tawang District 2 X 1500 kW Arunachal Pradesh Jan 2009 Completed
195. Nuranang DPR in Tawang District 2 X 1500 kW Arunachal Pradesh Jan 2009 Completed
194. Bafen Vihir in Maharashtra 1 X 10 kW MNRE 2007 Submitted
193. Baram SHP (Modification) in Pithoragarh 2 X 500 kW UREDA 2007 Submitted
192. Bhitri in Uttarakhand 2 X 20 kW MNRE 2007 Submitted
191. Bod in M.P. 1 X 10 kW MNRE 2007 Submitted
190. Changaria 1 X 50 kW + 1 X 50 kW MNRE 2007 Submitted
189. Cheelud SHP 2 X 50 kW UREDA 2007 Submitted
188. Dugtu 1 X 20 kW MNRE 2007 Submitted
187. Gavar Gaon in Chhattisgarh 2 X 20 kW MNRE 2007 Submitted
186. Goriya Deh in Jharkhand 1 X 50 kW MNRE 2007 Submitted
185. Kedarnath 1 X 20 kW MNRE 2007 Submitted
184. Khapugad MHP 1 X 20 kW UREDA 2007 Submitted
183. Khatwa in Uttarakhand 2 X 20 kW MNRE 2007 Submitted
182. Magra in Rajasthan 2 X 20 kW MNRE 2007 Submitted
181. Nada MHP in Rikhnargad 2 X 25 kW UREDA 2007 Submitted
180. Nagling 2 X 20 kW MNRE 2007 Submitted
179. Neora SHP in West Bengal 2 X 3000 kW Neora Hydro Ltd., Kolkata 2007 Under Progress
178. Obragad in Uttarakhand 2 X 50 kW MNRE 2007 Submitted
177. Pareng SHP in Arunachal Pradesh 2 X 3000 kW APEDA 2007 Submitted
176. Paro in A.P. 2 X 80 kW MNRE 2007 Submitted
175. Patu in A.P. 1 X 10 kW MNRE 2007 Submitted
174. PDD of Bundled SHP projects in Uttarakhand under CDM scheme CDM UREDA, Dehradun 2007 Completed
173. Pein SHP, Ph-I & II 2 X 3000 kW APEDA 2007 Under Progress
172. Ram Krishanpur in West Bengal 2 X 10 kW MNRE 2007 Submitted
171. Replacement of diesel operated vehicles by Battery operated vehicles in Dehradun CDM UREDA, Dehradun 2007 Completed
170. Sela 2 X 20 kW MNRE 2007 Submitted
169. Shikarpur in West Bengal 2 X 20 kW MNRE 2007 Submitted
168. Sie SHP in Arunachal Pradesh 2 X 2800 kW APEDA 2007 Submitted
167. Singrauli SHP (Updating) 2 X 4000 kW NTPC, Shakti Nagar 2007 Submitted
166. Uttarkashi & Borbalada 1 X 20 kW UREDA 2007 Submitted
165. Valmiki Nagar SHP and Dehri SHP 4 X 5 MW BSHPC, Bihar 2007 Under Progress
164. Review of Tunga in Karnataka 24 MW BMT Consultants Pvt. Ltd., Ahmedabad 2006 Submitted
163. Rongtong in HP 2000 kW HPSEB 2006 Under Progress
162. Rukti SHP in HP 1500 kW HPSEB 2006 Under Progress
161. Rajapur SHP - BSHP, Patna 2005-06 -
160. Ramgad-II in Uttaranchal 2 X 50 kW UREDA 2005-06 Submitted
159. Suringad SHP 300 kW UJVNL, Dehradun 2005-06 Under Progress
158. Uhl SHP in HP - Puri Oil Mills Ltd., New Delhi 2005-06 -
157. Updation - Mukto SHP in Ar.P. 3 X 1500 kW DHPD, Itanagar 2005-06 -
156. Niti SHP 2 X 25 kW Samiti and UREDA 2004-05 Under Progress
155.   2 X 500 kW J&KPDC 2004 Under Progress
154. 2 SHP in Uttaranchal - UREDA 2004 Completed
153. Palor-II, H.P. 2 X 1500 kW Manglam SHP, Noida 2004 Completed
152. Tarkiana on Canal Fall 2 X 100 kW PEDA, Punjab 2004 Completed
151. Kunnu Charang 2 X 100 kW HimUrja, Shimla 2003-04 Under Progress
150. Akbarpur SHP 2 X 250 kW NEDA, Lucknow 2003 Under Progress
149. Badarpur TPS-Tail Water SHP 1 X 400 kW NPTI, Faridabad 2003 Submitted
148. Betwa canal Head SHP 3 X 650 kW NEDA, Lucknow 2003 Under Progress
147. Betwa SHP 2 X 1000 kW NEDA, Lucknow 2003 Under Progress
146. Chudiyala SHP 2 X 250 kW NEDA, Lucknow 2003 Under Progress
145. Dabka river – Dabka 1 X 80 kW UREDA, Uttarakhand 2003 Completed
144. Dasna SHP 2 X 1000 kW NEDA, Lucknow 2003 Under Progress
143. Gunchai SHP 2 X 400 kW NEDA, Lucknow 2003 Under Progress
142. Jamini Dam-I 1 X 100 kW NEDA, Lucknow 2003 Under Progress
141. Jamini Dam-II 1 X 100 kW NEDA, Lucknow 2003 Under Progress
140. Kuthond-I SHP 2 X 350 kW NEDA, Lucknow 2003 Under Progress
139. Kuthond-II SHP 2 X 350 kW NEDA, Lucknow 2003 Under Progress
138. Manglay 2 X 1000 kW Deptt. Of Power, Sikkim 2003 Completed
137. Sikasar Dam 2 X 3500 kW Chhattisgarh State Electricity Board 2003 Completed
136. Updating/Revision of DPR - Bhalla SHP 2 X 750 kW J&KPDC, Jammu 2003 Under Progress
135. Updating/Revision of DPR - Brenwar SHP 2 X 1000 kW J&KPDC, Jammu 2003 Under Progress
134. Updating/Revision of DPR - Chingus SHP 2 X 300 kW J&KPDC, Jammu 2003 Under Progress
133. Updating/Revision of DPR - Mohumangath MHS 2 X 300 kW J&KPDC, Jammu 2003 Under Progress
132. Updating/Revision of DPR – Poonch SHP 2 X 250 kW J&KPDC, Jammu 2003 Under Progress
131. Updating/Revision of DPR – Tulei SHP 2 X 350 kW J&KPDC, Jammu 2003 Under Progress
130. Upgradation/Revision - Bogdong 2 X 350 kW J&K SPDC Ltd. 2003 Completed
129. Upgradation/Revision - Dah 2 X 1500 kW J&K SPDC Ltd. 2003 Completed
128. Upgradation/Revision - Dumkhar 1 X 200 kW J&K SPDC Ltd. 2003 Completed
127. Upgradation/Revision - Hanu 2 X 1500 kW J&K SPDC Ltd. 2003 Completed
126. Upgradation/Revision - Kumdok 3 X 75 kW J&K SPDC Ltd. 2003 Completed
125. Upgradation/Revision - Sasoma 2 X 250 kW J&K SPDC Ltd. 2003 Completed
124. Upgradation/Revision - Tangste 2 X 250 kW J&K SPDC Ltd. 2003 Completed
123. Chaksi 2 X 500 kW Puri Oil Mills 2002 Completed
122. Dhukwa Dam 2 X 15000 kW UP Jal Vidyut Nigam 2002 Submitted
121. Gandak – Saran Canal RD II 1000 kW BHPC, Patna 2002 Submitted
120. Gandak Saran RD-II 1000 kW BHPC, Patna 2002 Completed
119. Ghes 100 kW UREDA 2002 Under Progress
118. Lamchula 50 kW UREDA 2002 Under Progress
117. Main Canal – Golapar 1 X 150 kW UREDA, Uttaranchal 2002 Completed
116. Mukerian Stage-II 2 X 9000 kW PSEB 2002 Submitted
115. Nandhor Main river - Chorgalia 1 X 100 kW UREDA, Uttarakhand 2002 Completed
114. Rotan 50 kW UREDA, Uttarakhand 2002 Under Progress
113. Tarula 100 kW UREDA, Uttarakhand 2002 Under Progress
112. Uhl 2 X 1000 kW Puri Oil Mills 2002 Completed
111. Amritganga HE 500 kW NEDA, Lucknow 2001 Under Progress
110. Baran HE 1000 kW NEDA, Lucknow 2001 Under Progress
109. Jimigad HE 900 kW NEDA, Lucknow 2001 Under Progress
108. Lachen 2000 kW DOP, Sikkim 2001 Submitted
107. Manjusha 2 X 250 kW BHPC 2001 Completed
106. Miyagam BC SHP CH 4150 m 2 X 750 kW SSNNL, Gandhinagar 2001 Submitted
105. Miyagam BC SHP CH 6415 m 2 X 750 kW SSNNL, Gandhinagar 2001 Submitted
104. Miyagam BC SHP CH 7500 m 2 X 750 kW SSNNL, Gandhinagar 2001 Submitted
103. Miyagam BC SHP CH 8531 m 2 X 500 kW SSNNL, Gandhinagar 2001 Submitted
102. Miyagam BC SHP CH 9900 m 3 X 750 kW SSNNL, Gandhinagar 2001 Submitted
101. Miyagam BC SHP CH 16700 m 3 X 750 kW SSNNL, Gandhinagar 2001 Submitted
100. Rellichu 6000 kW DOP, Sikkim 2001 Submitted
99. Ringyang 1000 kW DOP, Sikkim 2001 Submitted
98. Rongli-I 5000 kW DOP, Sikkim 2001 Submitted
97. Telhargad 2 X 1000 kW BHPC 2001 Completed
96. Dhokti Gaon 1 X 20 kW UREDA, Uttarakhand 2000 Completed
95. Kanol Gad 2 X 50 kW UREDA, Uttarakhand 2000 Completed
94. Karmi-II 2 X 25 kW UREDA, Uttarakhand 2000 Completed
93. Ratmoli 2 X 25 kW UREDA, Uttarakhand 2000 Completed
92. Rawat Sera 1 X 50 kW UREDA, Uttarakhand 2000 Completed
91. San Gad 1 X 50 kW UREDA, Uttarakhand 2000 Completed
90. Satteshwar 2 X 25 kW UREDA, Uttarakhand 2000 Completed
89. Saurastra BC-Ch 5.15 km 2 X 8000 kW SSNNL, Gandhinagar 2000 Submitted
88. Saurastra BC-Ch 17.76 km 2 X 8000 kW SSNNL, Gandhinagar 2000 Submitted
87. Saurastra BC-Ch 32.94 km 2 X 8000 kW SSNNL, Gandhinagar 2000 Submitted
86. Valipur Fall 2 X 200 kW NEDA, Lucknow 2000 Submitted
85. Tarrit Tara mini hydel 2 X 1500 kW Deptt. Of Power, Govt. of Ar. P. 1998-99 DPR Completed
84. Ampani mini hydel - Deptt. Of Power, Govt. of Ar. P. 1998 DPR Completed
83. Baraf mini hydel - Deptt. Of Power, Govt. of Ar. P. 1998 Dropped
82. Dao mini hydel - Deptt. Of Power, Govt. of Ar. P. 1998 Under Preparation
81. Ganga mini hydel 2 X 250 kW Deptt. Of Power, Govt. of Ar. P. 1998 DPR Completed
80. Halaipani mini hydel 3 X 3000 kW Deptt. Of Power, Govt. of Ar. P. 1998 DPR Completed
79. Kakra Gad/Akash Kamini 2 X 20 kW UNDP-GEF 1998 Under Construction
78. Review of SHP Scheme at Tons I 2 X 1500 kW Subhash Projects & Marketing Ltd. 1998 Under Construction
77. Review of SHP Scheme at Tons II 2 X 1500 kW Subhash Projects & Marketing Ltd. 1998 Under Construction
76. Review of SHP Scheme at Tons III 3 X 5000 kW Subhash Projects & Marketing Ltd. 1998 Under Construction
75. Urinfall mini hydel - Deptt. Of Power, Govt. of Ar. P. 1998 Under Preparation
74. Wakka mini hydel - Deptt. Of Power, Govt. of Ar. P. 1998 Dropped
73. Hnahchanglui Mini Hydel Project 2 X 400 kW Power & Electricity Deptt., Govt. of Mizoram 1997-98 Completed
72. Chillong in Kargil 250 kW Power & Electricity Deptt., Govt. of Mizoram 1997 DPR Completed
71. Dah Hydel Scheme, Leh-Khalsi 3000 kW Deptt. Of Power, Govt. of Ar. P., Power & Dev. Deptt., J&K Govt. 1997 DPR Completed
70. Kanvaashram 2 X 50 kW UNDP-GEF 1997 Under Construction
69. Kumdong Leh 100 kW Power Dev. Corporation 1997 Submitted
68. Lingti SHP 2 X 200 kW HIM Urja, HP Govt 1997 Under Construction
67. Miyagam Branch Canal RD 2315 m 3 X 750 kW Sardar Sarovar Narmada Nigam Ltd. 1997 Submitted
66. Rambhadra Mini Hydel Project 2 X 1000 kW Deptt. Of Power, Agartala 1997 Submitted
65. Review of SHP Scheme at Birhiganga 2 X 1250 kW Subhash Projects & Marketing Ltd. 1997 Under Construction
64. Review of SHP Scheme at Rishiganga 2 X 3500 kW Subhash Projects & Marketing Ltd. 1997 Under Construction
63. Sekku mini hydel 3 X 250 kW Deptt. Of Power, Govt. of Ar.P. 1997 DPR Completed
62. Stakna State II 2.5 MW Power Dev. Corporation 1997 Under Preparation
61. Upshi-Igo Hydel Scheme 3000 kW Deptt. Of Power, Govt. of Ar.P., Power & Dev. Deptt., J&K Govt. 1997 Under Construction
60. Bogdong in Norba 200 kW Power Dev. Corporation 1996 Submitted
59. Farakka SHP 2 X 250 kW NTPC/FSTPS 1996 Submitted
58. Gangotri micro hydel 2 X 100 kW NEDA, Lucknow 1996 Under Construction
57. Hanu Hydel Scheme Leh-Khalsi 3000 kW Deptt. Of Power, Govt. of Ar.P., Power & Dev. Deptt., J&K Govt. 1996 DPR Completed
56. Hanuman Ganga Small Hydro Uttarkashi 2 X 1500 kW Regency Motels Paonta Sahib (HP) 1996 Under Construction
55. Jaidary Canal 2 X 100 kW Haryana State EB Yamuna Nagar 1996 DPR Submitted
54. Jugding mini hydel 3 X 1000 kW Deptt. Of Power, Govt. of Ar.P. 1996 Under Construction
53. Rina Mini Hydel, Along 4 X 500 kW Deptt of Power, Arunachal Pradesh 1996 Submitted
52. Sasoma Hydel Scheme in Nobra valley 3 X 300 kW Deptt. Of Power, Govt. of Ar.P., Power & Dev. Deptt., J&K Govt. 1996 DPR Completed
51. Siemen mini hydel 3000 kW Deptt. Of Power, Govt. of Ar.P., Power & Dev. Deptt., J&K Govt. 1996 DPR Completed
50. Subbong mini hydel 3 X 1000 kW Deptt. Of Power, Govt. of Ar.P. 1996 Submitted
49. Thusgam stage-I 2 X 100 kW Power Dev. Corporation 1996 DPR Completed
48. Augmentation Canal 2 X 500 kW Haryana State EB Yamuna Nagar 1995 Submitted
47. Jamar Kotra micro hydel 1 X 50 kW REDA, Jaipur 1995 Submitted
46. Jhamri dam micro 1 X 50 kW REDA, Jaipur 1995 Submitted
45. Rajouri small hydro 3 X 1000 kW Power Dev Corp, J&K Govt 1995  
44. Tukvar Tea Estate Small Hydro 2 X 200 kW Jayshree Tea Darjeeling 1995  
43. Korba Small Hydro Project 2 X 750 kW NTPC, Korba 1994 Submitted
42. Lower Ghagri Mini Hydel 2 X 200 kW Bihar State Hydro Electric Power Corporation, Patna 1994 Under Progress
41. Sadani Mini Hydel 2 X 500 kW Bihar State Hydro Electric Power Corporation, Patna 1994 Under Construction
40. Sippi Mini Hydel 3 X 1000 kW Deptt. of Power, Govt. of Ar.P. Naharlagun 1994 Under Construction
39. Deverebelkere Mini Hydel 2 X 1000 kW Karnataka Power Corporation Ltd., Bangalore 1993 Commissionned
38. Domkhorong Mini Hydel 2 X 1000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Ready for Commissioning
37. Feroz Gandhi Unchahar Thermal Power Project mini hydro power 1 X 250 kW NTPC, Unchahar 1993 Submitted to Govt.
36. Kambang Mini Hydel 2 X 1500 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Under Construction
35. Khangtang small hydel 3 X 2500 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Under Construction
34. Kitpi II mini hydel 3 X 1000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Under Construction
33. Kush mini hydel 2 X 1000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Under Construction
32. Liromoba Mini Hydel 2 X 1000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Under Construction
31. Mukto small hydel 3 X 3000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Under Construction
30. NTU Micro Hydel 1 X 100 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Submitted to Govt
29. Nuranang small hydel 3 X 2000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Commissioned
28. Pacha mini hydel 2 X 1000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Under Construction
27. Passighat-II mini hydel 2 X 250 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Submitted to Govt.
26. Payu mini hydel 2 X 500 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Submitted to Govt.
25. Siddip mini hydel 3 X 1000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Under Construction
24. Sigrauli Super TPS return canal fall SHP 2 X 1500 kW Sigrauli Super Thermal Power Station NTPS, Sonebhadra (UP) 1993 Under Construction
23. Sipit mini hydel 2 X 1000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Under Construction
22. Sirnyuk mini hydel 3 X 1000 kW Deptt.of Power, Govt. of Ar.P. Naharlagun 1993 Commissioned
21. Sarkari Mini Hydel 2 X 750 kW U.P. Laghu Jal Vidyut Nigam Ltd. 1991 State PIB cleared
20. Netarhat Micro hydel 1 X 50 kW Bihar State EB/BSHPC 1990 Under Construction
19. Bilkot Micro hydel 1 X 50 kW Non-Conventional Energy Development Agency, Govt. of U.P. 1989 Commissioned
18. Pantwari Micro hydel 1 X 50 kW Non-Conventional Energy Development Agency, Govt. of U.P. 1989 Dropped by State Govt.
17. Bahadrabad Mini Hydel 2 X 125 kW DNES & UPLJV 1987 Govt. sanction received
16. Baram Micro hydel 2 X 25 kW Non-Conventional Energy Development Agency, Govt. of U.P. 1987 Under consideration by State Govt.
15. Barboria mini hydel 2 X 150 kW DNES & OPGC 1987 Under Execution
14. Bargarh Mini Hydel 1 X 250 kW DNES & OPGC 1987 Under Construction
13. Kendupatna Mini Hydel 2 X 125 kW DNES & OPGC 1987 Commissioned
12. Khet Micro Hydel 2 X 50 kW Non-Conventional Energy Development Agency, Govt. of U.P. 1987 Commissioned
11. Killara (Pangi Valley) 3 X 100 kW DNES & HPSEB 1986 Commissioned
10. Ralla Mini Hydel 1 X 250 kW DNES & PSEB 1986 Govt. sanction received
9. Igo-Mercllong 3 MW Power Dev. Corporation   Under Preparation
8. Kalpong 500 kW A&N Island, Power Department    
7. Khara Small Hydro Electric Scheme 1500 kW Uttar Pradesh Jal Vidyut Nigam Ltd., Lucknow   Completed
6. Korang 200 kW A&N Island, Power Department    
5. Panchvati 200 kW A&N Island, Power Department    
4. Phyang in Leh 340 kW Power Dev. Corporation   Under Preparation
3. Rangat 200 kW A&N Island, Power Department    
2. Tangste-Nyoma Leh 300 kW Power Dev. Corporation   Submitted
1. Vasundhara 200 kW A&N Island, Power Department   Completed
# # # # # | # # #
Credits : Information Management Group, IIT Roorkee